Bill of Quantities in Kenya: How a BQ Is Prepared, Read and Priced

If you are planning a house, an apartment block or a commercial building, sooner or later someone will ask, “Do you have a BQ?” A bill of quantities Kenya contractors, banks and SACCOs can work from is one of the most useful documents in any project. It turns your architectural and structural drawings into a measured list of every item of work, from excavation to the last coat of paint, so that the job can be priced fairly and costs can be controlled once building starts.

We have already covered what a quantity surveyor does in Kenya and when to hire one. This guide goes one step further and looks at the document itself: what goes into it, how BQ preparation works, what a BOQ sample looks like and how to use a priced bill of quantities to compare bids. If you would rather have the work done for you, our quantity surveying and cost management services from Marble Engineering cover BQ preparation, tender analysis and cost control from design to handover.

Need a BQ for your project? Send us your drawings for a quote: WhatsApp 0789 217 685

What is a bill of quantities in Kenya?

A bill of quantities (BQ, sometimes written BOQ) is a document that lists, in a standard order, every item of work and material needed to build a project, with a clear description, a unit of measurement and a measured quantity for each item. Contractors then fill in a rate against each item, and the rate multiplied by the quantity gives the amount. Add up all the amounts and you have the tender sum.

In Kenya, BQs are standard for public tenders and for most serious private projects. Government agencies publish them openly with their tender documents. For example, the Kenya Revenue Authority’s published BQ for storm water and sewer rehabilitation works shows the typical layout: preambles and pricing notes, preliminaries, measured works, a main summary and a grand summary.

Quantity surveyors in Kenya are currently registered under the Architects and Quantity Surveyors Act (Cap. 525). A separate Quantity Surveyors Bill, 2026 was published in February 2026 and is before the National Assembly; it proposes a new Institute and Council to regulate the profession on its own. Whatever the outcome, the practical advice is the same: have your BQ prepared or checked by a registered quantity surveyor.

What a BQ contains: the main sections

Every quantity surveyor has a house style, but most building BQs in Kenya follow a similar order:

  • Preambles and pricing notes – the rules for pricing: what each rate must include (labour, materials, plant, waste, overheads and profit), how provisional work will be remeasured, and which specifications apply.
  • Preliminaries – site-wide costs that are not part of any single element: site set-up, hoarding, insurances, security, water and power for the works, site supervision and clean-up.
  • Measured works by element – usually substructure (excavation, foundations, ground slab), superstructure (frame, walling, roof, windows and doors, finishes) and external works.
  • Services – plumbing, drainage and electrical installations, often in their own bills.
  • Provisional sums and prime cost (PC) sums – allowances for work or items not yet fully designed or chosen, such as kitchen fittings or a borehole.
  • Contingency – a sum held for the unexpected, spent only on the client’s instruction.
  • Collections, main summary and grand summary – page totals are carried forward to give the final tender figure.

BOQ sample: how a bill page is laid out

A typical bill page uses six columns. The illustrative BOQ sample below shows the layout only; rates are left blank because they depend on the location, the specification and the market at the time of tender.

ItemDescriptionUnitQuantityRate (KSh)Amount (KSh)
AExcavate foundation trench not exceeding 1.5 m deep and cart away surplusm³[measured][contractor][qty × rate]
BConcrete class 20 in strip foundationsm³[measured][contractor][qty × rate]
C200 mm machine-cut stone walling in cement sand mortarm²[measured][contractor][qty × rate]
DHigh-tensile steel reinforcement bars, cut, bent and fixedkg[measured][contractor][qty × rate]
EProvisional sum for kitchen fittingsItem––[fixed allowance]
Illustrative bill of quantities layout (not a priced estimate).

Notice that each description is precise enough that two contractors would price the same thing. That precision is what makes a BQ valuable.

Bill of quantities Kenya – quantity surveyor preparing a priced BQ for a building project

BQ preparation: the step-by-step process

  1. Collect complete drawings. Architectural plans, sections and elevations, structural drawings and, ideally, MEP layouts. A BQ is only as good as the drawings behind it.
  2. Agree the specification. Walling type, roofing, floor finishes, window frames and fittings must be decided, or at least allowed for as provisional sums.
  3. Take-off. The quantity surveyor measures every item from the drawings – volumes of concrete, areas of walling and plaster, lengths of pipe, weights of steel.
  4. Write descriptions. Each measured item is described in standard terms so it can be priced without guesswork.
  5. Arrange the bills. Items are grouped by element and trade, with preliminaries, provisional sums and summaries added.
  6. Prepare an engineer’s or QS estimate. The QS prices the BQ independently to give the client a realistic budget before tender.
  7. Issue for tender. Contractors receive the unpriced BQ, fill in their rates and return a priced bill of quantities.

For a straightforward house with complete drawings, BQ preparation is usually a matter of days to a few weeks, depending on the size of the project and how much of the design is final.

How to use a priced bill of quantities to compare contractors

When several contractors price the same BQ, you can compare them line by line instead of comparing vague lump sums. Look out for:

  • Unrealistically low rates on big items such as concrete, steel or walling – a sign the contractor may claim variations later or cut corners.
  • Front-loading – high rates on early items (excavation, foundations) and low rates on later ones, which improves the contractor’s cash flow at your risk.
  • Blank or “included” items – ask exactly where those costs have gone.
  • Arithmetical errors – check quantity × rate on every line and the carried-forward totals.
  • Inflated preliminaries – compare them against the size and length of the job.

The lowest tender is not always the cheapest project. A properly analysed priced BQ helps you choose the contractor who is most likely to finish on budget.

Using the BQ during construction

The BQ does not stop being useful once a contractor is appointed. It becomes the basis for:

  • Interim valuations – the QS measures work done on site and values it at the BQ rates before each payment.
  • Variations – if you change the design, the cost of the change is worked out from existing BQ rates where possible.
  • Remeasurement – work marked “provisional” is measured again as built and paid on actual quantities.
  • Final account – the agreed final cost of the project at handover.
  • Financing – banks and SACCOs often ask for a BQ to assess a construction loan and release funds in stages.

For a sense of how these figures come together on real budgets, see our guides on the cost of building a 3 bedroom house in Kenya and how much a design and build project costs in Kenya.

Common BQ mistakes Kenyan clients make

MistakeWhat it causesHow to avoid it
Preparing a BQ from incomplete drawingsLarge variations and budget overrunsFinish structural and MEP design first, or mark items clearly as provisional
Using a contractor’s own BQ to compare other bidsQuantities may favour that contractorHave an independent QS prepare the bill
Copying a BQ from a “similar” houseWrong quantities for your plot, soil and designMeasure from your own drawings
No contingencyNo cushion when ground conditions or prices changeInclude a sensible contingency agreed with your QS
Treating the tender sum as finalSurprise at the final accountTrack variations and provisional sums monthly

Who should prepare your bill of quantities in Kenya?

For anything beyond a small extension, use a registered quantity surveyor who is independent of the contractor, or a design-build firm whose QS works for you from the start. Diaspora clients in particular benefit from a clear BQ, because it lets you see exactly what you are paying for at each stage without being on site. Ask to see an example of the firm’s previous bills, confirm registration, and agree up front whether the fee covers tender analysis, valuations and the final account.

Frequently asked questions

Is a BQ the same as a cost estimate?

No. A cost estimate can be a rough figure based on floor area. A bill of quantities is a detailed measured document that lists every item of work, and it can be priced to give a far more reliable estimate and a fair basis for tendering.

Do I need a BQ for a bank or SACCO construction loan?

Many lenders in Kenya ask for approved drawings and a BQ before approving a construction loan, and use it to release money in stages. Requirements differ between lenders, so confirm with yours early.

Can I prepare a BQ myself?

You can make a simple materials list, but a proper BQ needs accurate measurement, standard descriptions and current pricing knowledge. Errors in quantities quickly become disputes and overruns, so it is worth paying a professional.